§ 143B‑279.17.  Tracking and report on permit processing times.

The Department of Environmental Quality shall track the time required to process all permit applications in the One‑Stop for Certain Environmental Permits Programs established by G.S. 143B‑279.12 and the Express Permit and Certification Reviews established by G.S. 143B‑279.13 that are received by the Department. The processing time tracked shall include (i) the total processing time from when an initial permit application is received to issuance or denial of the permit and (ii) the processing time from when a complete permit application is received to issuance or denial of the permit. No later than January 1 of each odd‑numbered year, the Department shall report to the Joint Legislative Oversight Committee on Agriculture and Natural and Economic Resources, the Fiscal Research Division of the General Assembly, and the Environmental Review Commission on the permit processing times required to be tracked pursuant to this section. The Department shall submit this report with the report required by G.S. 143‑215.3A(c) as a single report. (2012‑187, s. 13(a); 2015‑241, s. 14.30(u); 2017‑10, s. 4.12(b); 2017‑57, s. 14.1(n).)